David Pittaway writes:

'pontoons are coming along slowly but consistently. The physical size of components demands a team approach, which has been well attended on Wednesday mornings. We have P1 fully framed up and ready for decking to go on. Any observers will have noticed a few extra scungy timbers incorporated into the framing. These have been added in anticipation of having to take the rolling load of the brow (engineer talk for walkway) which has been purpose bought for one pontoon. '

Pics in reverse order below show the progress: 
  • the current state of framing,
  • getting the framed up floats into the water,
  • and David removing the old decking.